School principal Brian Goggins shows plans for the new school to Minister Helen McEntee and LMETB CEO Martin O'Brien

"We don't have the luxury of waiting six weeks"

School community at O'Carolan College "shell-shocked" as Department of Education stalls building project days away from it proceeding to construction despite looming planning deadline

The Principal of O'Carolan College, Nobber, has said the entire school community is "shell-shocked" at news that their long-awaited new school is among 58 building projects stalled by the Department of Education.

Everything was ready to go on the project with the tender process completed and the school was awaiting the letter from the Department giving the final green light to proceed, with construction due to start in May.

Principal Brian Goggins said they "don't have the luxury of waiting six weeks" for the Department of Education to evaluate the list of projects as planning permission is due to expire and they need the green light now if they are to meet their planning deadlines.

New rules mean an extension to planning permission can no longer be applied for and if approval is not granted almost immediately to proceed, the school may have to begin the entire planning process again.

Mr Goggins is appealing to the Department of Education to make an exception for schools like Nobber where planning is due to expire.

"We are shell-shocked. We were literally days away from issuing a letter to start. We were at the end of the process. We had a big launch with Minister Helen McEntee, everyone was so excited and we were ready to go.

"This has been at the race track since 2004. We thought, finally we are at the last hurdle, waiting to announce that work was to start. We were already in pre-planning for works that needed to be carried out during June and July before school starts back.

"We are pulling our hair out."

Photo by null

Parents are said to be furious and bitterly disappointed that at this late stage, the project has been stalled.

Mr Goggins said they understand that there is a shortfall of money and and that word is to come back by Easter on the projects but said for them every day counts.

"An exception has to be made. They have to prioritise projects that are at this stage. There can't be any more than two or three nationally.

"We have a very short window to get this started. It was already tight. For us, every day counts. We need the letter today so we can get our project started.

"For some projects a delay of six weeks makes no difference, to us a delay of six weeks could put us back to the start and we would have to do the planning process all over again. It could be the death knell for us. We are ready to go now."

He said Minister Helen McEntee had taken a personal interest in the project and has been working hard in the background on it.

A new school was approved for O'Carolan College in 2014, with planning permission granted in 2018 for the 7,000 square metres three-storey school building to include specialist rooms, science labs, arts and crafts room, home economics room, construction engineering rooms and a multi-purpose hall big enough to hold the entire school community.

An artists impression of the new school Photo by Noelle Finegan

The tender process was complete, the report was with the Department of Education, and LMETB were awaiting permission from the Department to issue the letter of acceptance to the apparently successful tenderer.

Unless approval to proceed is given almost immediately, a spokesperson for LMETB said they will not be able to comply with the planning permission deadline and new rules mean there is no longer the option of applying for an extension of planning permission.

"Certain projects like O'Carolan College where there is a planning deadline to meet cannot wait until the government reflects on it. We need to be pulled out of the main pot.

"If we have to reapply for planning, there is the potential for objections. It means additional temporary accommodation will be needed and existing prefabs will have to be replaced. There will be a huge cost to provide temporary accommodation."

While the Department of Education has not published the list of 58 building projects that were at tender and construction stages that have been affected, Enfield Community College is also among them.

The project is understood to have been ready to go to tender for several months and just two weeks ago, the Meath Chronicle highlighted the huge frustration felt locally over the delay in progressing the permanent building for the 1,000 student school.

In correspondence to the affected schools, the Department of Education said it was currently assessing its work programme and priorities for 2023 in the context of overall requirements and available funding and is engaging with the Department of Public Expenditure, NDP Delivery and Reform.